Engineering/Road Construction
County Road 115 (Airport Road) Rehabilitation - Concrete Overlay
Location: Between Trunk Highway 22 and County Road 7 (school Road)
Anticipated Start of Construction: 4/29/24
Anticipated Open to Traffic: Late June 2024
Contractor: Croell, Inc., New Hampton, IA
Location: Between Trunk Highway 22 and County Road 7 (school Road)
Anticipated Start of Construction: 4/29/24
Anticipated Open to Traffic: Late June 2024
Contractor: Croell, Inc., New Hampton, IA
During construction the road will be closed to all thru traffic, but access will be maintained for individuals living along or doing business along the road. There will be a detour established.
The project is funded with Local Option Sales Tax and State Aid funds.
COUNTY ROAD 115 CONSTRUCTION UPDATE (4/23/24)
Pre-Construction survey work is complete. Milling is expected to begin on Monday 4/29/2024. A project open house will be held on 4/24/2024 at the McLeod County Fairgrounds Commercial Building Meeting room from 4 pm to 6pm.
County Road 115 (Airport Road) and County Road 25 (Jefferson Street) Roundabout Construction
Location: Intersection of County Road 115 (Airport Road) and County Road 25 (Jefferson Street)
Anticipated Start of Construction: May 2024
Anticipated Open to Traffic: Late August 2024
Contractor: Ramsey companies, Minneapolis, MN
Anticipated Start of Construction: May 2024
Anticipated Open to Traffic: Late August 2024
Contractor: Ramsey companies, Minneapolis, MN
This project includes the construction of a roundabout, partial reconstruction of Jefferson Street from Airport Road to Edmonton Avenue. . During construction the road will be closed to all thru traffic, but access will be maintained for individuals living along or doing business along the road.
A project open house will be held on 4/24/2024 at the McLeod County Fairgrounds Commercial Building Meeting room from 4 pm to 6pm.
A project open house will be held on 4/24/2024 at the McLeod County Fairgrounds Commercial Building Meeting room from 4 pm to 6pm.
County Road 115 Concrete Pavement Repair
Location: County Road 115 from County Road 7 (School Road) to Trunk Highway 7
Location: County Road 115 from County Road 7 (School Road) to Trunk Highway 7
Anticipated Start of Construction: Construction is scheduled to start Late July
Anticipated Open to Traffic:
Contractor: TI-Zack Construction, LeCenter, MN
Anticipated Open to Traffic:
Contractor: TI-Zack Construction, LeCenter, MN
The County Road 115 Concrete Pavement Repair Project includes removing and replacing settled and broken concrete pavement.
Highway 212/County Road 15 (Morningside) Roundabout Project
Highway 212/County Road 15 (Morningside) Roundabout Project